Haridaspur – Byree Section, a distance of 16.80KMs completed before target period

Bhubaneswar:28/5/23:The construction work for Bhadrak-Nergundi third line project in Howrah-Chennai Main line between Bhadrak and Cuttack Railway Stations under Khurda Road Division of East Coast Railway is going on in full swing. More than 50% of construction works of this project have been completed.

A patch of 16.80Kms between Haridaspur and Byree which was supposed to be completed by last week of June 2023 has been completed before 1st week of May’2023.

Image

This has been possible due to consistent review of project works by Hon’ble Minister of Railways Shri Ashwini Vaishnaw. General Manager Shri Manoj Kumar Sharma advised officials to focus for the speedy completion of various project works for the critical projects. Shri Sharma also advised officials to coordinate with stake holders including State Government officials for early completion of the projects.

Hon’ble Minister of Railways Shri Ashwini Vaishnaw is giving priority for the Development of Railway infrastructure of the region along with various project works going on in Odisha and also is monitoring the developmental works regularly. Bhadrak-Nergundi 3rd line work will boost the economy of the region and will provide a hassle free train operations in Howrah-Chennai Main Line.

Image

Bhadrak–Nergundi 3rd Line (92.19 Km) project was included in 2012-13 and the final Sanction was given in Oct’2015. Works between Jakhapura & Haridaspur, a stretch of 23.53KMs was completed in April 2016, from Kapilas Road to Salegaon, a stretch of 4.30 KMs was commissioned on May 2019 and from Kapilas Road to Nergundi, a distance of 4.20 KMs was commissioned on October 2022 in phased manner.

The target for completion of Bhadrak–Nergundi 3rd Line work has been decided to be by 2023-24, for rest 83.69 Kms work. The latest anticipated Cost of the Project is 1284.39 Crore, where Rupees 648.68 Crore has already been spent. The physical Progress for construction of full Project is about 54% and expenditure made about 50.5%.

About Editor in chief

Ashok Palit has completed his graduation from Upendranath College Soro, Balasore and post graduation from Utkal University in Odia Language and literture.. He has also carved out a niche for himself as a scribe of eminence after joining the profession in 1988. He is also an independent media production professional. He brings loads of experience to Advanced Media, Ashok Palit as a cineaste has been active in film criticism for over three decades. As a film society activist, he soared to eminence for his profound commitment to the art film appreciation and aesthetics of cinema. His mode of discourse is often erudite but always lucid and comprehensible marked by a perfect acumen so rare in the field. A film aesthete with an immense fond of critical sensibilities, he wrote about growth and development of odia cinema in New Indian Express, The Times of India, The Hindustan Times, The Asian Age and Screen. He has been working as an Editor for Cine Samaya from 2002-2004.. He had made solid contribution on cinema in many odia Dailies and weekly such as Samaj, Prajatantra, Dharatri, Samaya, Satabadi, and weekly Samaya.
x

Check Also

Paradip Port crossed an another milestone by handling 100 million tons (MT) of cargo in a record time

Bhubaneswar:10/12/24: Paradip Port in Odisha’s Jagatsinghpur district crossed another milestone by handling 100 million tons (MT) of cargo in a record time in 2024-25 financial year. Speaking to media persons, ...